土工膜的铺设方法-土工膜厂家教你土工膜施工
土工膜以塑料薄膜作为防渗基材,是一种高分子化学柔性材料,比重较小,延伸性较强,适应变形能力高,耐腐蚀,耐低温,抗冻性能好,具有较高的抗拉强度和延伸性,同时,它们对细菌和化学作用有较好的耐侵蚀性,不怕酸、碱、盐类的侵蚀,在避光使用情况下,使用寿命长达70年以上。
HDPE土工膜的铺设:
1. 铺设HDPE土工膜前应由土建工程相应的合格验收证明文件。
2. HDPE膜裁切之前,应该准确丈量其相关尺寸,然后按实际裁切,一般不宜按图示尺寸裁切,应逐片编号,详细记录在表格上。
3. 铺设HDPE土工膜时应力求焊缝少,在保证质量的前提下,尽量节约原材料。同时也容易保证质量。
4. 膜与膜之间接缝的搭接宽度一般不小于10cm,通常就使焊缝排列方向平行于坡度,即沿坡度方向排列。
5. 通常在拐角及畸形地段,应是接缝长度尽量减短。除特殊要求外,在坡度大于1:6的斜坡上距顶坡或应力集中区域1.5米范围内,尽量不设焊缝。
6. HDPE土工膜在铺设中,应避免产生人为褶皱,温度较低时,应尽量拉紧,铺平。
7. HDPE土工膜铺设完成后,应尽量减少在膜面上行走、搬动工具等,凡能对HDPE膜造成危害的物件,均不应放在膜上或携带在膜上行走,以免对膜造成意外损伤。
HDPE土工膜锚固方法:
1. 锚固的方法分为三种:沟槽锚固、射钉锚固和膨胀螺栓锚固;通常情况下,采用沟槽锚固。
2. 采用沟槽锚固时,视HDPE土工膜的使用条件及受力情况,其锚固沟槽宽度一般不小于0.5m-1.0m,其深度不得小于0.5m-1.0m。
3. 采用射钉锚固时,压条宽度不小于2cm,厚度不得小于2mm,射钉间距不应大于400mm,压条明露处应有防腐措施。
4. 采用膨胀螺栓锚固时,螺栓直径不小于4mm,其间距不大于0.5mm,施工时,先用备好的沙袋将摆好位置的膜临时固定,防止大风将HDPE土工膜吹动移位,然后再进行膨胀螺栓锚固。
Geomembrane paving method - geotechnical membrane manufacturers teach you geomembrane
Geomembrane to impervious plastic film as substrate, is a kind of polymer chemistry flexible material, small specific gravity, extension of strong, high adaptability to deformation, corrosion resistance, low temperature resistance, good freeze resistance, high tensile strength and extension, at the same time, their effect on bacterial and chemical action has better corrosion resistance, not afraid of acid, alkali, salt erosion, in the lightof use cases, long service life of 70 years.
HDPE geomembrane laying:
1 HDPE geomembrane laying before the civil engineering a corresponding qualification and acceptance certificate.
2 HDPE film cut before, should measure the correlation dimension, then according to the actual cutting, the general should not be to press the cutting size, should one piece number, recorded in detail in special form.
3 laying HDPE geomembrane should strive to weld the least, under the premise of guaranteeing quality, as far as possible to save raw material. It is also easy to ensure quality.
4 membrane and membrane joints between lap width not less than 10cm, usually make welds arrangement direction parallel to the maximum slope, along the slope direction.
Normally in the corner and deformity of 5 lots, should be the length of the joint to reduce short. Except special requirement, the slope is greater than 1:6 slope away from the top of slope and the stress concentration area within 1.5 meters, as far as possible without weld.
6 HDPE geotechnical membrane in laying, should avoid artificial fold, when the temperature is low, should betaut, paving.
7 HDPE geomembrane laying is completed, should be minimized in the membrane surface running, move tool, that can HDPE membrane damage objects, shall not put in the film or carried in the film walk, so as to avoid accidental injury of membrane.
HDPE geotechnical membrane anchoring method:
1 anchoring method is divided into three kinds: groove anchorage, nail anchoring and expansion bolt;typically, the groove anchorage.
2 the groove anchorage, as HDPE geomembrane using condition and stress condition, the anchoring groove width not less than 0.5m-1.0m, its depth shall not be less than 0.5m-1.0m.
3 the nail anchor, strip width not less than 2cm, thickness shall not be less than 2mm, nail spacing should not be greater than 400mm, Jo Aki dew point is due preservative measures.
4 the expansion bolt, the bolt diameter not less than 4mm, the distance is less than 0.5mm, construction, first with the prepared sandbags to set the position of the membrane temporary fixing, preventing the HDPEgeomembrane wind shift, then expansion bolt.
土工膜的铺设方法-土工膜厂家教你土工膜的铺设焊接施工方法 。